Sofware installation

The first step was to install the software MPLAB X IDE with the compiler XC 16 and to add all the required libraries and files to start coding for the dev board. To do so, we used the tutorial by Tony Colin and Brice Duhautois *link

Erasure code tests

In order to get acquainted with the equipment, we tested the code provided by Tony Colin and Brice Duhautois. We downloaded all the necessary files and we put it under a MPLAB X project. We first tested it on the simulator and then we loaded it on the developpement board. We observed the expected results both in the simulator and with the leds on the developpement board.

Test with Erasure code project
p=. Test with Erasure code project
Figure 1: Test with the Erasure Code

Test with the spectrum analyser

We plugged the RF transmitter on the developement board and we loaded a simple program to send a serie of 1.

Preliminary Test using a voltmeter

Second Set up

Results on the Spectrum analyser
Figure 3: Test with the spectrum analyser